Table C.1.5-1. Key Project Milestones
| Key Project Milestone/Activity | Target Start Date | Target Completion Date |
| Contract Award | NA | May 12, 2008 |
| Project Kickoff Meeting | 5 Days After Contract Award (DACA) | 15 DACA |
| Delivery of Laptop Kits – Baseline Configuration | 15 DACA | 30 DACA |
| Integrated Baseline Review | 45 DACA | 60 DACA |
| CAPI Project Support Website – Design Review | 45 DACA | 60 DACA |
| Delivery of Laptops Kits – Development Configuration | July 1, 2008 | July 31, 2008 |
| CAPI Project Support Website – Submitted for Acceptance | NA | August 1, 2008 |
| Maintenance Support Services – Ready for Operations | NA | October 1, 2008 |
| Delivery of Laptop Kits – Pilot Configuration | November 1, 2008 | November 10, 2008 |
| Delivery of Accessories and Supplies – Initial Stock | Per Order Instructions | Per Order Instructions |
| Delivery of Laptop Kits - Deployment Configuration | April 15, 2009 | July 15, 2009 |
| Delivery of Laptop Kits – CCM Configuration | May, 2010 | July, 2010 |
| Delivery of Laptop Kits – Post-Deployment Configuration | Per Order Instructions | Per Order Instructions |
| Delivery of Accessories and Supplies – Replenishment Stock | Per Order Instructions | Per Order Instructions |